Onboarding & Installation Planning Guide - Automatic Greasing System Solution
WELCOME TO GREASEBOSS
This guide has been prepared to help you and your team understand the next steps in the implementation process. It outlines:
- What to expect during installation and commissioning
- The roles typically involved in the installation
- Information required from your team
- Resources and support available throughout the process
Our team will work closely with your organisation to ensure the installation and commissioning process runs smoothly. This document simply ensures everyone involved has the information they need to prepare.
WHO SHOULD READ THIS GUIDE
This guide may be useful for several members of your team who will be involved in the system installation and operation, including:
- Maintenance Managers
- Reliability Engineers
- Maintenance Planners / Schedulers
- Mechanical Fitters
- Electricians or Auto Electricians
- IT / OT Teams
- Asset Management Personnel
Sharing this document with the relevant people in your organisation will help ensure a smooth and efficient implementation.
WHAT TO EXPECT – IMPLEMENTATION OVERVIEW
The implementation of the GreaseBoss system follows a straightforward process from planning through to commissioning and training.
Timeline/Steps Overview
|
Stage |
What Happens |
Who Is Involved |
|
1 |
Installation Planning Meeting |
Customer Team + GreaseBoss |
|
Confirm Network / IT Requirements |
Customer IT/OT Teams |
|
|
2 |
Deployment |
|
|
Populate Asset Details and Data Details Confirmation for Cloud |
Customer Team |
|
|
Establish and Configure Cloud Account | Ship Hardware |
GreaseBoss |
|
|
3 |
Installation – Endpoints and Gateways |
Mechanical Fitters + Electricians |
|
4 |
System Commissioning & Data Verification |
GreaseBoss + Customer Team |
|
5 |
Handover, Further Training and Enhanced Support |
GreaseBoss + Customer Team |
INSTALLATION PLANNING MEETING
The first step in the process is to schedule an Installation Planning Meeting.
This meeting ensures everyone involved understands the installation plan and responsibilities before work begins.
We recommend including the following people where possible:
- Maintenance supervisor
- Reliability engineer
- Maintenance planner or scheduler
- Mechanical fitter supervisor
- Electrical supervisor
- IT / OT representative
The purpose of the meeting is to:
- Confirm the assets that will be monitored
- Review the installation approach
- Confirm installation locations
- Review communication/network requirements
- Assign installation personnel
- Schedule installation works
Following this meeting, GreaseBoss will prepare installation work orders in the Hindsite Mobile Application and supporting documentation.
GREASEBOSS GREASECLOUD DASHBOARD ACCESS
The GreaseBoss Cloud Dashboard is where system data is displayed and where system configuration is managed.
Before system commissioning, please consider which personnel in your organisation will require access to the platform.
Typical users may include:
- Reliability engineers
- Maintenance supervisors
- Asset managers
- Operations managers
Please provide the following information for each user:
|
Name |
| Email Address | |
Permission Level |
Common permission levels include:
- Site Admin – full system configuration access and user administration
- Manager – Some system configuration access
- General User – Read-only access
For more details on user permissions and access, view this information in our Knowledge Base: https://knowledge.greaseboss.com.au/manage-users-permissions-explained-site-admins
PLANNERS/SCHEDULERS
Maintenance planners, schedulers, or project coordinators play an important role in ensuring the GreaseBoss installation is completed efficiently and safely within existing site workflows.
Crew and Equipment Resources Required during the installation can include:
|
Crew/Resource |
Task / Requirement |
Required/Optional |
|
Fitters |
Install Endpoint |
Required |
|
Auto Electrician / Electrician |
Install Gateway |
Required |
|
Hose & Fittings Suppliers |
Make Hoses and have Fittings available on site |
Optional (if site has hoses premade and fittings sourced and all delivered prior to install) |
|
Boilermakers |
Fabricate Brackets if required |
Optional (Brackets not required if using supplied Mag Mounts for Endpoints) |
|
EWP & Operator |
Access points where Endpoints are to be installed at hieghts (ie: on boom or stick of excavator or arms of loader) |
Optional (dependent on asset and installation location of Endpoint). |
Estimated Duration Of Installation
|
Asset Installation Type |
First Time Installing |
When Experienced |
|
Haul Truck |
1 day |
0.5 day |
|
Excavator / Loader |
2 days |
1 – 1.5days |
|
Fixed Plant |
(Dependent on number of Endpoints to be installed |
|
Scheduling Considerations
When planning installation works, the following factors may need to be considered:
- Asset availability
- Maintenance shutdown windows
- Crew availability
- Access to grease lines and lubrication systems
- Electrical access for gateway installation
- Safety and permit requirements
GreaseBoss will assist your planning team in determining the estimated time and resources required for installation.
PROCUREMENT OF HOSES, FITTINGS & ADDITIONAL ANCILLARY COMPONENETS
The installation of the GreaseBoss System components will require the procurement of additional hoses, fitting and ancillary components.
Prior to installation, consider and conform the following:
- The number and type of fittings required to install the Endpoints in line of the grease system lines
- The hoses type, length and size required to install the Endpoints in line of the grease system lines
- Confirm the locations the Endpoints will be installed and measure distances from grease points to assist with hose lengths.
- Have a hose and fitting supplier on site during the install to make hoses and supply fittings to suit and accommodate changes in planned install locations
- Determine if Endpoints will be mounted using supplied Mag Mounts or if will need to have a bracket fabricated to be installed.
|
Components |
Considerations |
|
Endpoint to Hose Fittings |
|
|
Hoses |
|
|
Brackets |
|
|
Protective Plates |
|
IT / OT REQUIREMENTS
In some cases, the GreaseBoss system may require review or approval from IT or OT teams to confirm compliance with site network and cybersecurity policies.
Possible connectivity options include:
- LTE / cellular communication
- Site WiFi
- Ethernet connection
- Private operations networks
The IT / OT team may be required to assist with:
- Approving the selected network communication method
- Providing network access details where required
- Confirming firewall or security requirements
- Ensuring compliance with site cybersecurity policies
If your organisation requires IT approval processes, we recommend IT or OT team being involved early in the planning phase.
For further details about Network Communications options and requirements, please see the following links:
Backhaul & Data Setup Explainer Video
Data Communications Architecture Options
GreaseBoss Information Security Policy
INSTALLERS – MECHANICAL FITTERS
Authorised mechanical fitters are responsible for installing the GreaseBoss Endpoint Devices into the asset’s automatic lubrication system lines.
Installation Guides
Installation Guides for the GreaseBoss Endpoints can be found HERE
Before installation, fitters should confirm:
1. Grease Line Identification
- Which grease point the device will monitor
- The associated grease line
2. Device Installation Location
- Exact mounting location on the asset
- Access and safety considerations
3. Mounting Method
- Magnetic mount
- Custom bracket
- Supplied mounting bracket
4. Required Hardware
- Hydraulic fittings
- Grease hoses
- Mounting hardware
5. Device Commissioning
Fitters will also need to:
- Sync the device with the GreaseBoss Gateway
- Confirm device operation
Work Orders
GreaseBoss will supply a Work Order with individual work instructions and installation guides within the Hindsite Work Order App. Fitters will be assigned to these work orders and can access them through a mobile device.
Visit: www.hindsiteind.com
INSTALLERS – ELECTRICAL
Qualified electricians or auto-electricians are responsible for installing the GreaseBoss Gateway and Antennas.
Installation Guides for the Gateways and Antenna can be found HERE:
Before installation, the Electrician should confirm:
Gateway Installation
- Mounting location
- Environmental requirements
- Power supply connection
Antenna Installation
- LTE antenna location
- BLE antenna location
- Optimal signal positioning
Power Supply
- Confirm correct voltage source
- Ensure proper protection and isolation
Commissioning
- UPS or Battery PSU to Energise the gateway for Testing during installation
- Confirm device communication
- Verify system connectivity
Work Orders
GreaseBoss will supply a Work Order with individual work instructions and installation guides within the Hindsite Work Order App. Fitters will be assigned to these work orders and can access them through a mobile device.
Visit: www.hindsiteind.com
SUPPORT
If you require assistance at any stage during installation or commissioning, the GreaseBoss team is available to help.