HME installation Procedure - Mobile equipment

 

 

Installation overview

step 1 - determine the ideal endpoint location for install

step 2 - perform range testing to confirm connectivity with devies and gateway

step 3 - install the gateway

step 4 - install the endpoints

 

Determine ideal endpoint installation location

where applicable it is best practice to install the endpoints directly or as close as possible to the bearing or point

note: the Endpoint MP2 also measures pressure so you have more flexibility on install location.

perform range testing

 
 
 

steps

 

step 1 - install the gateway

  • install gateway in electrical cabinet or similar weatherproof environment

  • externally mount bluetooth antennae

    • you may need to consider a different install location so leave this as a “loose” / temporary install until connectivity confirmed

  • connect backhaul configuration

    • externally mount LTE antennae if required.

    • connect LAN cable if required

  • once gateway is powered and operational proceed to step 2

IMG_5558 
 IMG_5557
 
 

step 2 - range testing

  • walk to each point location

  • with an endpoint device hold the the endpoint as close as possible to install location and perform a manual sync

  • if all points have a successful sync proceed to INSTALL THE ENDPOINT

  • if a point has an unsuccessful sync

    • confirm with a minimum of 3 attempts

    • consider gateway BT antenna install location. the BT and devices have a range of 50m+ , but significant structrual steel can impede the signal.

    • consider endpoint install location

      • running a longer hose to a location within range

 

image-20250527-035058 

 

 

 

 

 

 
 

Install the endpoint

 
 
 

Steps

images

Once connectivity confirmed

  • Install the endpoints as desired

  • The bulk flow is the only endpoint to have a flow direction for install considerations.

  • all other endpoints measure flow regardless of direction of flow

 GD955 Grader - Photo 1-1
 20250204_172421

IMG_2567 2

 

Endpoint MP2

  • ¼" BSPP Female inlet and outlet port threads

  • 4x M4 Bolts, Bracket or Magnet Mount options

EMP2 on Loader (1) EMP2 on injector bank (1)
 

 

Hardware features

  1. LED light

  2. Button

  3. Port 2

  4. Port 1

 image-20250605-063624 (1)

 

Hardware features

  1. Port 1 identifier notch

This notch in the profile identifies the closest port as Port 1. for reference during install and cloud assignment.

 

image-20250605-063640

 

Hardware features

  • Serial number

  • QRCODE for mapping in the GB APP

image-20250605-063926